Foundation Brick Work Complete

The brick has been going on the foundation quickly. All this work was done in a day. Unfortunately, it appears they’ve ran out before being able to complete the front porch and rear foundation bump out. Hoping they get more brick in soon and the work continues.





Update 7/31 @ 11:13 AM: Additional bricks were delivered and now the foundation brick work is complete. We really love the way the look of the brick has turned out!


Bricks Delivered

A shipment of bricks has been delivered and placed around the foundation. The bricks appear to be a dark red color but have a sand coating on the outside that lightens them up. It will be interesting to see how they look once they are put on and how much of that dark-reddish color shows through.

Basement Walls Poured

Tina and I have been out of town in Cleveland for my heart valve replacement surgery. So, we’ve had to send my sister and Barb to go take pics of the progress and send them over to us. The concrete walls have been poured and forms have been removed. Here’s a few pics and a video walk around of the basement in its current state.