Woodwork & Countertop Replacement

There has been a lot of work completed at the house this week. The wood stair treads leading up to the second story and guard rails have been installed and are waiting to be stained. The deck portion of the sun room has also been completed. The next step is to have the screened walls and stairs put in. Also, the frameless glass shower door in the master en suite has been installed, and all the bathroom vanity countertops have replaced.

Stair treads have been installed leading up to the second story
Guard rail work is complete
Wood will be stained to match the hardwood flooring in the rest of the house
Another view of the wood work that was recently completed
Deck work is well underway
View from the sliding glass doors out to the deck
Now that the deck work is complete, the next step is enclosing the screen room
The frameless glass shower doors have been installed in the master en suite
The replacement vanity countertops are finally in
We definitely appreciate the subtle gray swirling in this manufacturer’s product

Here are the items still left to complete:

  • Interior clean up, paint and trim touch up, – Scheduled for this coming week
  • Carpet installation – TBD
  • Appliance delivery, installation – TBD
  • Sun room screens and deck stairs – TBD
  • Gutters, downspouts, extend drainage pipes around basement of house – TBD
  • Stone accents in front of house, around fireplace, install chimney cap – TBD
  • Final grading, landscaping, irrigation installation – TBD
  • Power wash exterior, second coat of paint – TBD

Punch list items:

  • Replace spray foam over sprayed roof shingles
  • Repair damaged brickwork
  • Replace damaged window trim

2 Replies to “Woodwork & Countertop Replacement”

  1. Everything looks SO GOOD!!! πŸ˜€πŸ‘πŸ»πŸ‘πŸ»πŸ‘πŸ»πŸ‘πŸ»πŸ€­πŸ’•πŸ’•πŸ’•πŸ’•

  2. That kitchen tho…. spectacular home, Congratulations!!!! πŸŽŠπŸΎπŸŽˆπŸŽ‰

    πŸ€­πŸ’•πŸ’•πŸ’•

Leave a Reply

Your email address will not be published. Required fields are marked *